Phase 2 refinery almost mirror those in phase 1, which has two CDUs of 200,000 b/d each.
ZPC expects to complete construction of the secondary units by the end of first-half 2021, the source said.
The first CDU in phase 2 has been on trial run since Nov. 1, 2020. The source said its utilization rate has been gradually lifted, resulting in the three CDUs at the complex to run at average 100% in February from about 70% in the previous months.
With the commissioning of the second CDU at the phase 2 refinery, ZPC is set to double its total refining capacity to 800,000 b/d.(Source)
Asset Info
- Category
- Processing
- Status
- A
- V
Technology
- Technology
- Generic ADU
- Licensor
- Undefined Technology Provider
Additional Info
- Utilization Planning
- Asset Level
- UoM
- Barrels
System Settings
- User
-  Kokel, Nicolas
- Added
- 11/24/2024 5:51 PM
  Units Quick Access
Unit | D | Technology-Unit | Category |
---|---|---|---|
Default Unit |
|