Golden Pass Products LLC (GPP) is a Delaware-organized limited liability company focused on LNG export from the United States. It operates as the export development entity of the broader Golden Pass LNG complex located at Sabine Pass, Texas. The company achieved a major milestone in March 2026, producing its first LNG from Train 1 of its 3-train, 18 million tons per annum (mtpa) export facility.
Origins: The Import Terminal Era (2003–2010)
Golden Pass Products LLC traces its roots to the early 2000s, when rising U.S. energy demand prompted QatarEnergy (then Qatar Petroleum) and ExxonMobil — along with a third partner, ConocoPhillips — to develop an LNG import terminal on the Texas Gulf Coast. The Golden Pass LNG import project formally commenced in November 2003, with the goal of supplying U.S. markets with Qatari LNG. Construction of the associated Golden Pass Pipeline was completed in 2009, and the terminal itself was completed in 2010, receiving its first LNG cargo in October 2010 aboard the Al Khuwair Q-Flex vessel.
The Shale Revolution and Strategic Pivot (2012–2019)
The U.S. shale gas boom fundamentally changed the company's outlook. By around 2012, domestic natural gas supply estimates exceeded 100 years of consumption, rendering the import model largely redundant. Golden Pass adapted by pivoting toward LNG export. In October 2012, Golden Pass Products LLC filed with the U.S. Department of Energy for permission to export LNG to free-trade-agreement (FTA) nations — a permit that was granted the same month. A broader non-FTA export authorization followed on April 25, 2017, covering all additional countries under the Natural Gas Act. During this period, the import terminal remained operational and on standby as a strategic energy security asset.
Final Investment Decision and Construction (2019–2024)
The shareholders took the pivotal Final Investment Decision (FID) on February 5, 2019, committing over $10 billion to build three liquefaction trains (3 × 5.2 mtpa = 15.6 mtpa total) adjacent to the existing terminal. The EPC contract was awarded to a joint venture of Zachry Holdings and Chiyoda Corporation. Concurrently, in June 2019, Golden Pass Products LLC was formally merged into Golden Pass LNG Terminal LLC as part of a corporate consolidation of the export project entities. Construction progressed steadily, targeting a 2024 Train 1 startup, but the project encountered severe setbacks when lead contractor Zachry Holdings filed for Chapter 11 bankruptcy in May 2024 due to escalating project costs. At the time of Zachry's exit, Train 1 was approximately 83% complete, Train 2 at 46%, and Train 3 at 31%.
Recovery and First LNG (2024–2026)
Following a settlement reached in July 2024, Chiyoda Corporation took over as sole EPC lead, and construction momentum was restored. By February 2026, the facility was receiving over 300 million cubic feet of natural gas daily in preparation for commissioning. First LNG from Train 1 was achieved in March 2026, marking the culmination of more than two decades of development and a defining milestone for the project. With Trains 2 and 3 still progressing, Golden Pass LNG is on track to become one of North America's largest LNG export facilities upon full operations.