Jomoro Phase One Refinery
Entity
Jomoro Petroleum Refining & Processing Company Ltd.
Site in a Project-Phase
/ Jomoro
Western Region
Off Tikobo 1 – Half Assini Nawulley
PHDC Project Office
Insight Articles
#SI960

Description

Current Status: Pre-Construction / Land Acquisition Phase

Despite the August 2024 groundbreaking ceremony presided over by then-President Nana Akufo-Addo, actual on-site construction has not yet commenced as of early 2026. Petroleum Hub Development Corporation (PHDC) CEO Dr. Toni Aubynn formally declared 2026 the "Year of Action" in January 2026, stating the project is shifting from planning to tangible on-site activity. The key bottleneck remains land acquisition — in April 2026, PHDC confirmed it is still in the process of acquiring the project land, with the Executive Instrument (the legal mechanism transferring the land to the state for the project) expected to be completed by July 3rd, 2026 and final publication will be done by Mid of August 2026. The PHDC Board backed management's push to start physical on-site work in 2026.


Refinery Technical Profile (Jomoro I)

Full PHase One asset specifications are as follows:

Asset Capacity / Detail
Refinery 300,000 bpd crude processing (cracking complex)
Petrochemical Plant 90,000 bpd; produces fertilizers, lubricants, cosmetics-grade chemicals using natural gas as feedstock
Storage Tank Farm 3,000,000 m³ total capacity
Jetty & Marine Port Crude import + refined product export terminal
Ancillary Power plant, LNG facility, water treatment, metering & calibration lab, fabrication workshop

Feedstock & Market Strategy

The refinery will process imported crude oil (Ghana's own offshore production — primarily from Jubilee and TEN fields — is relatively modest at ~150,000 bpd and already committed). The hub's Free Zone status means it is primarily export-oriented, targeting the West African regional market for refined products, which currently imports the majority of its fuel needs. The petrochemical plants will use natural gas as feedstock, leveraging Ghana's associated gas resources.


Key Milestones & Timeline

Milestone Status
Development agreement signed ✅ June 2024
Groundbreaking ceremony ✅ August 2024
Environmental & community engagement ✅ Ongoing
Executive Instrument (land transfer) 🔄 On track for July 2026
Physical on-site works start 🔄 Targeted before 2026 end
Phase One full completion 🎯 ~2030–2031 (realistic estimate)
All three phases complete 🎯 2036

Project Challenges

Several issues have slowed progress beyond the groundbreaking:

  • Community compensation — affected landowners and residents in Jomoro require resettlement and compensation payments; PHDC CEO engaged Parliament specifically on this issue in mid-2025

  • Land size revision — the hub's total area was reduced from 20,000 to 12,300 acres (5,000 ha) following community consultations, though PHDC states this does not affect project scope

  • Political transition — the change of government (President Mahama replacing Akufo-Addo after the December 2024 election) required re-engagement; Dr. Aubynn met President Mahama in November 2025 and confirmed continued government support

  • Environmental concerns — proximity to the Amanzule Wetlands (a Ramsar-listed site) has raised NGO and civil society scrutiny


References

  1. PHDC Instagram (April 21, 2026) — Confirms land acquisition in progress, Executive Instrument on track for July 2026; physical site works targeted for 2026.
    instagram.com/p/DXY8wLUF_ef
  2. GhanaWeb (January 16, 2026) — Dr. Toni Aubynn declares 2026 the "Year of Action" for the Petroleum Hub project.
    ghanaweb.com — 2026 Year of Action
  3. PHDC.gov.gh (February 6, 2026) — PHDC Board backs management's push to begin on-site work in 2026.
    phdc.gov.gh — Board backs 2026 start
  4. The High Street Journal (January 23, 2026) — Ministry of Energy and Green Transition backs PHDC at 2025 performance review; 2026 plans outlined.thehighstreetjournal.com — Ministerial support
  5. Daba Finance (August 22, 2024) — Groundbreaking ceremony details, construction timeline, and TCP-UIC consortium role.
    dabafinance.com — Construction kickoff
  6. Jomoro Municipal Assembly (April 2025) — Confirms land size reduction from 20,000 to 12,300 acres and land acquisition meeting timelines.
    jma.gov.gh — News
  7. PHDC.gov.gh (April 14, 2026) — Revised 12,300-acre land plan gains support from Jomoro chiefs and political authorities.
    phdc.gov.gh — Revised land plan
  8. Construction Review Online (November 18, 2025) — Comprehensive project overview including asset specifications, Free Zone status, and export strategy.constructionreviewonline.com — Jomoro petroleum hub
  9. African Energy Council (November 18, 2025) — Update on Jomoro oil refinery project scope, feedstock strategy, and West African market positioning.africanenergycouncil.org — Jomoro update
  10. PHDC.gov.gh (June 9, 2025) — CEO engages Parliament on community compensation and land acquisition challenges.
    phdc.gov.gh — Parliamentary engagement
  11. GhanaWeb (June 26, 2024) — Nzema Coalition raises conditions on land acquisition: generational compensation, 25% equity, 30% job quota, environmental safeguards.
    ghanaweb.com — Nzema Coalition
  12. Gas Outlook (October 7, 2024) — Covers environmental concerns, proximity to Amanzule Wetlands (Ramsar site), and civil society scrutiny.
    gasoutlook.com — Environmental concerns
  13. PHDC.gov.gh (April 12, 2025) — PHDC CEO Dr. Toni Aubynn Makes First Official Visit to Jomoro, Site of Ghana’s Ambitious Petroleum Hub.
    phdc.gov.gh — Aubynn visit Jomoro
  14. PHDC Facebook (May 4, 2026) — Community engagement update confirming $60bn total project cost and 20,000-acre full site extent.
    facebook.com/phdcgh

Insight Articles
Insights from our Experts

2026/05/28 05:55 AM

PHDC Petroleum Hub Structure Plan (Phasing Plan) | Adapted from: Land Use and Spatial Planning Authority (May 2021)


Market Insights | ppPLUS Intelligence Series • Refining & Petrochemicals | May 2026

Click here for full content
Title Date
  UserPic Created Project Site 9/3/2024
Feasibility
Project Stage:
Feasibility
Completion Date:
12/2030